EU project
BALTICON S.A., with the registered office in Gdynia at ul. Tadeusza Wendy 15, implements the project no. POIS.03.02.00-00-0051 / 18 under the name “Construction of an intermodal terminal for reloading of containers in road-rail or rail-road relations, container storage and services necessary for the functioning of intermodal container transport “. The project is co-financed by the European Union under the Infrastructure and Environment for 2014-2020 Operational Programme.
Ladies and Gentlemen,
We would like to inform you that in connection with implementing the project entitled “Construction of an intermodal terminal for reloading of containers in road-rail or rail-road relations, storage of containers and services necessary for the operation of intermodal container transport”, we have decided to extend the deadline for its implementation until December 31st 2022. On June 2nd 2020 we signed an annex to the Co-Financing Agreement as the Beneficiary. Current project data:
Annex to the Co-Financing Agreement no.POIS.03.02.00-00-0051 / 18-01
Date of signing the Annex to the Co-Financing Agreement: June 2nd 2020.
Project implementation time: January 1st 2019 – December 31st 2022.
Planned total cost of the Project implementation: PLN 36,083,472.19
Maximum amount of eligible expenses: PLN 22,523,400.00
Maximum amount of co-financing from the EU funds: PLN 11,261,700.00
Project purpose:
The main objective of the project is constructing an intermodal terminal in Gdańsk located in the TEN-T network.
Project scope:
The project includes: construction of an intermodal terminal (approx. 6 hectares), construction of a water and sewage system, storm water drainage, power engineering and lighting infrastructure, as well as purchase of specialist equipment necessary to operate the terminal.
Main tasks performed under eligible costs:
Construction of a storage and reloading yard together with construction of networks and connections,
Purchase of terminal operating equipment,
Supervision of construction works,
Project management (including project implementation and settlement),
Informative and promotional activities.
Reporting of irregularities:
The Managing Authority of the Infrastructure and Environment Programme attaches particular importance to ensure that the Programme projects are implemented in a way that is:
– ethical,
– open,
– transparent.
Therefore, there was created a tool to report any irregularities related to projects financed with the Infrastructure and Environment Programme funds.
Below you will find a link to report irregularities regarding projects financed with the Infrastructure and Environment Programme funds.
https://www.pois.gov.pl/strony/zglaszanie-nieprawidlowosci/
Project calendar:
19.07.2022 - signing a contract with Cargotec Poland Sp. z o.o. for supplying two terminal tractors for the Balticon S.A. terminal together with maintenance service.
12.07.2022 - announcing the supplier of two terminal tractors for the Balticon S.A. container terminal together with maintenance service (winning offer: Cargotec Poland Sp. z o.o., ul. Metalowa 2, 73-102 Stargard, Poland)
30.06.2022 - deadline for submitting offers for supplying two terminal tractors and two terminal trailers for the Balticon S.A. container terminal together with maintenance services
24.05.2022 - publication of the request for quotation as concerns supplying two terminal tractors and two terminal trailers for the Balticon S.A. container together with maintenance services
06.05.2022 - completion of constructing the sub-stage 2.2. of the second stage of construction works - completion of the terminal construction
31.01.2022 - signing with Cargotec Poland Sp. z o.o. a contract for supplying carts for container reloading (Reachstacker and Empty Container Handler).
26.01.2022 - announcing the supplier of carts for container reloading (Reachstacker and Empty Container Handler) (winning offer: Cargotec Poland Sp. z o.o., Metalowa 2, 73-102 Stargard, Poland)
18.01.2022 - deadline for submission of bids for supplying carts for container reloading (Reachstacker and Empty Container Handler)
16.12.2021 - publication of the request for quotations for submitting carts for container reloading (Reachstacker and Empty Container Handler)
30.11.2021 - meeting business partners as a part of the project promotion
29.09.2021 - completion of constructing sub-stage 2.1. of the second stage of construction works
20.05.2021 - handover of the construction site to the Contractor
10.05.2021 - signing a contract for Execution of Construction Works with Firma Budowlano - Drogowa MTM SA
05.05.2021 - announcing the Contractor of Construction Works – 2nd stage (winning bid: Firma Budowlano - Drogowa MTM SA)
26.04.2021 - deadline for submitting bids for the Contractor of Construction Works – 2nd stage
25.03.2021 - publication of the request for quotation for the Contractor of Construction Works – 2nd stage
19.03.2021 - signing a contract for the Investment Supervision Inspector function
19.02.2021 - announcing the Investment Supervision Inspector (winning offer: PRO-INSTAL Franciszek Żukowski)
05.02.2021 - deadline for submitting bids for the Investment Supervision Inspector function
26.01.2021 - publication of the request for quotation for the Investment Supervision Inspector function
18.06.2020 - signing an agreement to terminate the contract for the Investment Supervision Inspector function
02.06.2020 - signing an annex to the contract for co-financing No.POIS.03.02.00-00-0051 / 18-01, extending the project completion date until December 31st 2022.
16.01.2020 - obtaining a permit for the 1st stage
18.12.2019 - completion of the first stage construction works
03.06.2019 - handover of the construction site to the Contractor
28.05.2019 - signing a contract for Construction Works with Firma Budowlano - Drogowa MTM SA
26.03.2019 - announcing the Contractor for the 1st stage Construction Works (winning bid: Firma Budowlano - Drogowa MTM SA)
08.03.2019 - deadline for submitting bids for the Contractor of the 1st stage Construction Works
28.01.2019 - publication of the request for quotation for the Contractor of the 1st stage Construction Works
25.01.2019 - signing a contract for the project implementation and settlement
18.01.2019 - announcing the Contractor of the project implementation and settlement (winning bid: MF PROJEKT Monika Frygier)
16.01.2019 - deadline for submitting bids for the Contractor of the project implementation and settlement
08.01.2019 - publication of the request for quotation for the Contractor of the project implementation and settlement
21.12.2018 - signing a contract for co-financing between Balticon S.A. and CUPT
07.11.2018 - Balticon S.A. received a positive decision on the project co-financing
30.08.2018 - signing a contract for the Investment Supervision Inspector function
21.06.2018 - announcing the Investment Supervision Inspector (winning bid: Terma-Instal Przedsiębiorstwo Instalacyjne Wykonawstwo-Projektowanie inż. Łukasz Żukowski)
06.06.2018 - deadline for submitting bids for the Investment Supervision Inspector function
23.05.2018 - publication of the request for quotation for the Investment Supervision Inspector function