BALTICON S.A., with the registered office in Gdynia at ul. Tadeusza Wendy 15, implements the project no. POIS.03.02.00-00-0051 / 18 under the name “Construction of an intermodal terminal for reloading of containers in road-rail or rail-road relations, container storage and services necessary for the functioning of intermodal container transport “. The project is co-financed by the European Union under the Infrastructure and Environment for 2014-2020 Operational Programme.

Ladies and Gentlemen,

We would like to inform you that in connection with implementing the project entitled “Construction of an intermodal terminal for reloading of containers in road-rail or rail-road relations, storage of containers and services necessary for the operation of intermodal container transport”, we have decided to extend the deadline for its implementation until December 31st 2022. On June 2nd 2020 we signed an annex to the Co-Financing Agreement as the Beneficiary. Current project data:

Annex to the Co-Financing Agreement no.POIS.03.02.00-00-0051 / 18-01
Date of signing the Annex to the Co-Financing Agreement: June 2nd 2020.
Project implementation time: January 1st 2019 – December 31st 2022.
Planned total cost of the Project implementation: PLN 36,083,472.19
Maximum amount of eligible expenses: PLN 22,523,400.00
Maximum amount of co-financing from the EU funds: PLN 11,261,700.00

Project purpose:

The main objective of the project is constructing an intermodal terminal in Gdańsk located in the TEN-T network.

 Project scope:

The project includes: construction of an intermodal terminal (approx. 6 hectares), construction of a water and sewage system, storm water drainage, power engineering and lighting infrastructure, as well as purchase of specialist equipment necessary to operate the terminal.

 Main tasks performed under eligible costs:

Construction of a storage and reloading yard together with construction of networks and connections,

Purchase of terminal operating equipment,

Supervision of construction works,

Project management (including project implementation and settlement),

Informative and promotional activities.

Reporting of irregularities:

 The Managing Authority of the Infrastructure and Environment Programme attaches particular importance to ensure that the Programme projects are implemented in a way that is:

ethical,

open,

transparent.

  Therefore, there was created a tool to report any irregularities related to projects financed with the Infrastructure and Environment Programme funds.

Below you will find a link to report irregularities regarding projects financed with the Infrastructure and Environment Programme funds.

https://www.pois.gov.pl/strony/zglaszanie-nieprawidlowosci/

Project calendar:

19.07.2022 - signing a contract with Cargotec Poland Sp. z o.o. for supplying two terminal tractors for the Balticon S.A. terminal together with maintenance service.

12.07.2022 - announcing the supplier of two terminal tractors for the Balticon S.A. container terminal together with maintenance service (winning offer: Cargotec Poland Sp. z o.o., ul. Metalowa 2, 73-102 Stargard, Poland)

30.06.2022 - deadline for submitting offers for supplying two terminal tractors and two terminal trailers for the Balticon S.A. container terminal together with maintenance services

24.05.2022 - publication of the request for quotation as concerns supplying two terminal tractors and two terminal trailers for the Balticon S.A. container together with maintenance services

06.05.2022 - completion of constructing the sub-stage 2.2. of the second stage of construction works - completion of the terminal construction

31.01.2022 - signing with Cargotec Poland Sp. z o.o. a contract for supplying carts for container reloading (Reachstacker and Empty Container Handler).

26.01.2022 - announcing the supplier of carts for container reloading (Reachstacker and Empty Container Handler) (winning offer: Cargotec Poland Sp. z o.o., Metalowa 2, 73-102 Stargard, Poland)

18.01.2022 - deadline for submission of bids for supplying carts for container reloading (Reachstacker and Empty Container Handler)

16.12.2021 - publication of the request for quotations for submitting carts for container reloading (Reachstacker and Empty Container Handler)

30.11.2021 - meeting business partners as a part of the project promotion

29.09.2021 - completion of constructing sub-stage 2.1. of the second stage of construction works

20.05.2021 - handover of the construction site to the Contractor

10.05.2021 - signing a contract for Execution of Construction Works with Firma Budowlano - Drogowa MTM SA

05.05.2021 - announcing the Contractor of Construction Works – 2nd stage (winning bid: Firma Budowlano - Drogowa MTM SA)

26.04.2021 - deadline for submitting bids for the Contractor of Construction Works – 2nd stage

25.03.2021 - publication of the request for quotation for the Contractor of Construction Works – 2nd stage

19.03.2021 - signing a contract for the Investment Supervision Inspector function

19.02.2021 - announcing the Investment Supervision Inspector (winning offer: PRO-INSTAL Franciszek Żukowski)

05.02.2021 - deadline for submitting bids for the Investment Supervision Inspector function

26.01.2021 - publication of the request for quotation for the Investment Supervision Inspector function

18.06.2020 - signing an agreement to terminate the contract for the Investment Supervision Inspector function

02.06.2020 - signing an annex to the contract for co-financing No.POIS.03.02.00-00-0051 / 18-01, extending the project completion date until December 31st 2022.

16.01.2020 - obtaining a permit for the 1st stage

18.12.2019 - completion of the first stage construction works

03.06.2019 - handover of the construction site to the Contractor

28.05.2019 - signing a contract for Construction Works with Firma Budowlano - Drogowa MTM SA

26.03.2019 - announcing the Contractor for the 1st stage Construction Works (winning bid: Firma Budowlano - Drogowa MTM SA)

08.03.2019 - deadline for submitting bids for the Contractor of the 1st stage Construction Works

28.01.2019 - publication of the request for quotation for the Contractor of the 1st stage Construction Works

25.01.2019 - signing a contract for the project implementation and settlement

18.01.2019 - announcing the Contractor of the project implementation and settlement (winning bid: MF PROJEKT Monika Frygier)

16.01.2019 - deadline for submitting bids for the Contractor of the project implementation and settlement

08.01.2019 - publication of the request for quotation for the Contractor of the project implementation and settlement

21.12.2018 - signing a contract for co-financing between Balticon S.A. and CUPT

07.11.2018 - Balticon S.A. received a positive decision on the project co-financing

30.08.2018 - signing a contract for the Investment Supervision Inspector function

21.06.2018 - announcing the Investment Supervision Inspector (winning bid: Terma-Instal Przedsiębiorstwo Instalacyjne Wykonawstwo-Projektowanie inż. Łukasz Żukowski)

06.06.2018 - deadline for submitting bids for the Investment Supervision Inspector function

23.05.2018 - publication of the request for quotation for the Investment Supervision Inspector function

494995b1ff4d70d87389e558829bbce5.PLAC_12_Easy-Resize.com

66234e86a1c5d0210d8a2e26957e6d97.IMG_0088_Easy-Resize.com

c4a033b7f891b1360a4d9217461e2db7.IMG_0121_Easy-Resize.com

af26cf552ad672d6a1baa2a4363c8c7c.IMG_0133_Easy-Resize.com

mapadotacji

Contact us.
We are happy to answer your doubts!